Black Cat’s 100%-owned Mt Clement Antimony Project is located in the eastern Pilbara region of Western Australia, 30km from the Company’s producing Paulsens Gold Operation.
Status
In Production
Ownership
0%
Processing Capacity
0ktpa
Resource
@ 4.0 g/t Au
0Moz
(Including UG Resource of 0.4Moz @ 9.5 g/t Au)
There is substantial scope for Resource growth at Mt Clement, with only about 20% of the mapped vein system having been historically drilled.
Drilling targeting Resource growth and infill drilling to support economic studies for the optimisation of development pathways has been undertaken.
A 6,904m diamond drill program took place at Mt Clement during FY26 with visible antimony intersected in the first four holes completed.
In addition to drilling, the Company is steadily advancing the Mt Clement Antimony Project, conducting metallurgical test work and advancing technical studies to support project evaluation.